BALLAST NEDAM CHOOSES PVE2335 VM: The swelling clamp system


Ballast Nedam Funderingstechnieken (foundation engineering) and Dieseko joined forces to place about 7,000 tons of sheet-piling and combination wall in the province of Limburg, where the soil requires a special approach. All this took place in the period between December 2004 and mid-April 2005.

More...


Our clients are frequently confronted with a lack of space at the job site when vibrating the sheet-piles. In many cases this means that the sheet-pile clamp needs to be twisted under the vibro.

More...
INTRODUCTION OF THE SHEET PILE PRESSER, THE PVE 4125 CIVIL GEO!
The persistent demand in the market and particularly the order from our client Liebherr for the production and delivery of such a machine, prompted Dieseko to proceed with the development of this PVE machine.




More...
Piling projects in Singapore is getting very tough. The firm clay soil, doesn’t favour vibro work, only above average models can do the job here.






More...
THE LATEST RING VIBRATOR: THE PVE 20VMR      Retiring

In the successful range of ring vibrators, PVE now presents the smallest version of these models, the PVE 20VMR.


More...

 
Wim van Geenen: retiring after 30 years.



More...
PVE110M IN SAKHALIN PROJECT RUSSIA All disciplines in one hand
In the past decade, Quattrogemini Ltd. international contractors, a design and project management contractor from Finland, has been a name of stature for American and European investors in Russia. The management have decades of experience working in Russia and are therefore able to manage any project from the earliest phase and complete it within the agreed time, budget and quality standards.



More...
Within the Van Es Group, we now have a wide range of products and services available. You can turn to us to lease or buy:

• Cranes
• Jack-up Barges
• more

More...
BUILDING A NEW CONTAINER BERTH CT IV IN BREMERHAFEN DIESEKO POWER UNITS:
‘Hansenstad’ Bremerhafen is extending its existing container berth by approximately 870 metres. The essential part of this new berth is a combination wall consisting of double Hoesch PSp sections that are driven in at their target depth at a 2.31 metre centreto-centre distance, as well as Hoesch Pzi 675-12 intermediate slabs to fill the spaces between the PSp sections.


More..
For sale and rent

It is generally known that Dieseko Verhuur delivers power units for its hydraulic vibros. What the general audience is perhaps less familiar with is the fact that Dieseko also designs customized power units...

More...
Improved insertion methods with reduced noise and vibration levels PVE'S LARGEST VIBRATOR, THE PVE 200M, IN EGYPT
Dieseko, in collaboration with Gebr. De Koning b.v., conducted a vibration test at the construction site of ProRail at the lapwijkseweg in Pijnacker. During this test, sheet-piling and tubular poles were inserted using a PVE VM vibro. IFCO underingsexpertise performed vibration measurements in the vicinity of the vibration source, as well as noise level measurements.

More...
The insertion of tubes with a large diameter and a deadweight of 300 tons requires special
equipment indeed. This is no problem for Dieseko. We will find a solution for every obstacle.